Headbox Replacement

Menominee, MI

Industry: Pulp and Paper

Project Scope

CR Meyer was contracted by the equipment manufacturer to replace the headbox on Paper Machine #2 at a customer in Menominee, Michigan. The scope of work included replacing the headbox and installing new primary and dilution screens, attenuator, save-all pans, flume, and new platforms, walkways, and stairs. CR Meyer designed the monorails, platforms, walkways, and stairs.

Project Stats

  • Self-performed: Civil, Structural, Millwrighting, and Pipe Installation
  • Steel: 10 Tons
  • Concrete: 400 Cubic Yards
  • Pipe: 2,000 Feet
The quality of work and management helped these start-ups set a new benchmark for the machines. CR Meyer demonstrated their ability to be the general contractor of major installations by quickly resolving any subcontractor trades or billing issues and coordinating multiple disciplines in a limited work space.
Paper Industry Customer