Anderson, SC

CB3 Converting Lines

CBC Converting Lines

Project Summary

Our pulp and paper customer needed to expand their converting capacity with four new production lines — and needed a contractor who could coordinate complex, multi-system installations with precision, on time and on budget.

Duration
10 months

Key Challenges: Installing 4 Converting Lines with Zero Margin for Error

Adding four converting lines to an active tissue facility is not a straightforward equipment installation. Each line required a fully integrated web of supporting systems: process piping and tubing spanning steam, condensate, chilled water, and compressed air; a fire suppression system; electrical and controls; overhead bridge cranes; and air handling and broke handling equipment. Every system had to be installed in the right sequence, tested, and integrated with existing facility infrastructure — all with more than 100 field personnel on site at peak.

Solution

CR Meyer managed and executed the full converting installation scope across all four lines simultaneously, coordinating mechanical, piping, electrical, and controls work under a single project team. The fire suppression system, overhead cranes, and all air and broke handling equipment were installed and commissioned as part of an integrated delivery. The project was completed in 10 months.

Keys to Success

Multi-line coordination: Running four converting line installations in parallel demanded precise trade sequencing and daily coordination — CR Meyer’s self-perform capability across piping, electrical, and equipment installation made that possible under one accountable team.

Integrated systems delivery: Rather than treating each system as a separate scope, CR Meyer coordinated the fire suppression system, overhead cranes, and process piping as part of a single integrated installation plan, reducing interface risk between vendors and trades.

Schedule execution: With more than 100 field personnel at peak and a 10-month completion target, CR Meyer delivered on time, demonstrating the workforce depth and project management discipline that complex converting installations demand.

Project Stats

  • Overall value: Over $16 million
  • 4 converting lines installed
  • Peak employees on site: Over 100
  • Duration: 10 months
Topics
Pulp & Paper Electrical Piping Working in Active Facilities