Drummond Island, MI

Screening & Conveying System Installation

Project Summary

A mining customer needed to replace aging infrastructure and increase material conveyance capacity at their Drummond Island quarry operation. The solution required civil, structural, and mechanical construction across a working mining site, delivered on a compressed timeline.

Duration
6 months

Key Challenges: Upgrading a Live Quarry Operation Without Disrupting Production

The project required complete civil, structural, and mechanical infrastructure construction to support new screening and conveying systems at an active limestone quarry. New conveyor foundations, screen tower foundations, and a full structural steel screen tower had to be built, followed by the installation of two new vibratory screens, process piping, and 970 linear feet of new conveyors. Working within a live quarry environment meant managing safety, dust, and heavy equipment traffic while construction was underway — with the site’s ongoing production needs setting a firm end-date.

Solution

CR Meyer self-performed concrete, process piping, structural steel erection, and equipment installation across the full project scope. The screen tower was designed, built, and outfitted with new vibratory screens and conveyors in a six-month construction window. By keeping all critical trades in-house, CR Meyer maintained schedule control and minimized risk at the interface between construction activity and ongoing quarry operations.

Keys to Success

Single-source delivery: CR Meyer self-performed every critical trade — concrete, structural steel, process piping, and equipment installation — eliminating subcontractor coordination risk on a site where schedule delays had direct production consequences.

Live-site construction management: Working within an active quarry required disciplined site logistics, daily coordination with quarry operations, and a safety program built for industrial mining environments. CR Meyer delivered without production interruption.

Efficient six-month execution: The entire civil, structural, and mechanical scope — from foundations to commissioned conveyors — was completed in six months, demonstrating the project execution discipline that asset-intensive industries require.

Project Stats

  • Project value: $3.5 million
  • 650 CY of concrete
  • 130 tons of structural steel
  • 970 LF of new conveyors installed
  • 2 new vibratory screens
  • 25,000 manhours
  • Duration: 6 months
CR Meyer’s team helped us keep a complex project moving without losing sight of safety, schedule, or the details that mattered most.
Plant Operations Manager