2A/3A Lamella Replacement

Fernandina Beach, FL

Industry: General Industrial

Project Scope

CR Meyer was contracted by the equipment manufacturer to remove the existing lamellas and install the newly designed equipment. This scope included new steam chests, entrainment separators, and associated piping. The new lamellas showed up in halves and were preassembled in the laydown area prior to the outage utilizing CRM gantries. The lamellas weighed 50,000 lbs. when assembled. A 450 Ton crane with a pick radius of 70’ was used to remove / install the lamellas.

A challenge with the project was that the 2A evaporator was inoperable. This caused the mill to shut down the unit early which created a large amount of liquor to solidify inside the vessel. As a result, additional shifts were required to jackhammer, clean, and replan the demolition of the existing lamellas.

 

Everyone was extremely impressed with how quickly and efficiently the CR Meyer crew was able to get the additional braces and extensions in place. I received multiple compliments on how well they worked and how easy they were to work with.
Paper Industry Customer