Project Scope

The New Steam Turbine included the following: Turbine Building, MCC Room, Steam Turbine, Equipment Foundation, Wood Yard Upgrade, Boiler Modifications, Cooling Tower Foundations, Pipe Bridge Structures, Steam/Miscellaneous Piping, and Underground Process Piping.

Project Stats

  • Overview: Boiler Upgraded
  • Biomass Handling System New Turbine Generator
  • Duration: 13 Months
8 days after start-up - the Paper Machine has safely achieved the five-day average end-of-curve rates for yield, waste, and uptime 20 days ahead of the start-up curve! This is a huge accomplishment and we cannot thank you enough for your contributions.