Project Scope

The New Steam Turbine included the following: Turbine Building, MCC Room, Steam Turbine, Equipment Foundation, Wood Yard Upgrade, Boiler Modifications, Cooling Tower Foundations, Pipe Bridge Structures, Steam/Miscellaneous Piping, and Underground Process Piping.

Project Stats

  • Overview: Boiler Upgraded
  • Biomass Handling System New Turbine Generator
  • Duration: 13 Months
Everyone was extremely impressed with how quickly and efficiently the CR Meyer crew was able to get the additional braces and extensions in place. I received multiple compliments on how well they worked and how easy they were to work with.
Paper Industry Customer