New Tissue Machine Project

Pryor, OK

Industry: Pulp and Paper

Project Scope

CR Meyer was the general contractor responsible for the removal of two existing Tissue Machines to make room for a new Tissue Machine. The scope of the project included: removal of two Tissue Machines; removal and replacment of Machine Track Foundations; installation of two Sheet Pile Pits for UTM pulper and Fan Pump inside existing Machine Room; installation of one new Tissue Machine; a new Mezzanine for Yankee Air System; and Whitewater upgrades, including Concrete Flum and Chest.

Project Stats

  • Duration: 5 months (alongside an operating Tissue Machine)
Everyone was extremely impressed with how quickly and efficiently the CR Meyer crew was able to get the additional braces and extensions in place. I received multiple compliments on how well they worked and how easy they were to work with.