Roof Raise

Waupaca, WI

Industry: General Industrial

Project Scope

CR Meyer removed and reinstalled a portion of buildings to accommodate a new meshbeltmachine. We utilized our Manitowoc 1400 crane with full luffing jib to reach across other portions of the facility to complete the project. The project included demolition, underground utilities, shoring, concrete work, structural steel, cladding, siding, fire protection, roofing, windows/doors, machine install, and piping (air/roof drains).

Project Stats

  • 16.5 Tons of Rebar
  • 276 Tons of Steel
  • 206 Cubic Yards of Concrete
8 days after start-up - the Paper Machine has safely achieved the five-day average end-of-curve rates for yield, waste, and uptime 20 days ahead of the start-up curve! This is a huge accomplishment and we cannot thank you enough for your contributions.
Paper Industry Customer