Project Scope

CR Meyer was contracted by the equipment manufacturer to replace the headbox on Paper Machine #2 at a customer in Menominee, Michigan. The scope of work included replacing the headbox and installing new primary and dilution screens, attenuator, save-all pans, flume, and new platforms, walkways, and stairs. CR Meyer designed the monorails, platforms, walkways, and stairs.

Project Stats

  • Self-performed: Civil, Structural, Millwrighting, and Pipe Installation
  • Steel: 10 Tons
  • Concrete: 400 Cubic Yards
  • Pipe: 2,000 Feet
CR Meyer played a key role as a partner in the overall success of our project. The entire construction team was fully engaged and committed to delivering the successful results of being under budget, starting up early and attaining end-of-curve production in unprecedented time.
Paper Industry Customer