Coated Paperboard Machine
Waco, TX
Industry: Pulp and Paper
Project Scope
CR Meyer was chosen to build a new facility for a state-of-the-art coated recycled paperboard (CRB) machine. The 119-acre campus will be home to 640,000 square feet in production and warehousing facilities.
The project included:
- Preparation of roads, parking, site grading, utilities, rail service, steam production, fresh water supply, fire protection, and site security
- Construction of Finished Goods Warehouse, Fiber Line Facility, Fiber Line Warehouse, Paperboard Machine Facility, Administration and Maintenance Buildings
- Installation of Voith Fiber Prep System and a new Valmet Coated Paperboard Machine
Project Stats
- 640,000 SF
- 94,000 CY – Concrete
- 11,000 Ton – Steel
- 164,928 LF – Fabricated Pipe
- 380,200 LF – Overall Pipe & Tube