Renewable Energy Project

Quinnesec, MI

Industry: Hydro/Power Generation

Project Scope

The New Steam Turbine included the following: Turbine Building, MCC Room, Steam Turbine, Equipment Foundation, Wood Yard Upgrade, Boiler Modifications, Cooling Tower Foundations, Pipe Bridge Structures, Steam/Miscellaneous Piping, and Underground Process Piping.

Project Stats

  • Overview: Boiler Upgraded
  • Biomass Handling System New Turbine Generator
  • Duration: 13 Months
I would like to thank you for the mechanics that were sent down during the Outage to work on this project. It was a real joy to work with a great group of guys. Hope to work with CR Meyer in the near future.
Paper Industry Customer