New Tissue Machine Project

Pryor, OK

Industry: Pulp and Paper

Project Scope

CR Meyer was the general contractor responsible for the removal of two existing Tissue Machines to make room for a new Tissue Machine. The scope of the project included: removal of two Tissue Machines; removal and replacment of Machine Track Foundations; installation of two Sheet Pile Pits for UTM pulper and Fan Pump inside existing Machine Room; installation of one new Tissue Machine; a new Mezzanine for Yankee Air System; and Whitewater upgrades, including Concrete Flum and Chest.

Project Stats

  • Duration: 5 months (alongside an operating Tissue Machine)
Thanks to all of you at CR Meyer for the safe and professional work on this difficult rebuild as well as advice on potential improvements. We look forward to working with you in the future.