Baghouse Replacement

Green Bay & Eden, WI

Industry: Mining

Project Scope

CR Meyer was responsible for demolition of the old dust collection equipment and installation of a new ID fan, stack, baghouse, and all related foundations. The foundations required blasting of the bedrock. In addition, the scope of work included new pipe and supports from one side of the plant to the other as well as a new instrumentation package.

Project Stats

  • Lean Crete: 300 Yds
  • Concrete: 400 Yds
  • Steel: 22 Tons
  • Rebar: 23 Tons
CR Meyer has been a valuable partner to assisting us with our capital expansion projects. I am particularly impressed with their project planning process and their strong emphasis on safety during construction.
Mining Industry Customer