Headbox Replacement

Menominee, MI

Industry: Pulp and Paper

Project Scope

CR Meyer was contracted by the equipment manufacturer to replace the headbox on Paper Machine #2 at a customer in Menominee, Michigan. The scope of work included replacing the headbox and installing new primary and dilution screens, attenuator, save-all pans, flume, and new platforms, walkways, and stairs. CR Meyer designed the monorails, platforms, walkways, and stairs.

Project Stats

  • Self-performed: Civil, Structural, Millwrighting, and Pipe Installation
  • Steel: 10 Tons
  • Concrete: 400 Cubic Yards
  • Pipe: 2,000 Feet
I would like to thank you for the mechanics that were sent down during the Outage to work on this project. It was a real joy to work with a great group of guys. Hope to work with CR Meyer in the near future.
Paper Industry Customer